Projects

Drax Biomass, UK

Denman are providing commissioning support to assist with the conversion of Drax Power Station from a coal to a biomass plant.

Denman are providing instrument commissioning engineers and technicians.

The scope of work consists of the control of all instrumentation on the Drax Phoenix Eco store project. This includes: assigning them to correct locations, checking installation against P&ID’s, the setting up of a calibration workshop and pre calibration of instruments, testing signalling back to DCS, cold commissioning of individual systems through to hot commissioning and start up. 

The scope of work also includes testing all instrumentation back to the Drax DCS on all Robson conveyers and transfer towers.